Pigs Eye Lake Transmission

Project Overview

The existing 115 kV transmission network near Pigs Eye Lake Regional Park was built in the 1960s and has reached the end of its expected operational life. Xcel Energy plans to rebuild the infrastructure to meet continued electric reliability in the region. The project will modernize and enhance the performance of the transmission lines, ultimately improving reliability and minimizing the risk of outages.

The project will entail separating the existing two circuit transmission lines onto their own structures to ensure redundancy and reliability for customers in the area. Additionally, in recent years, national electric codes have been updated, and infrastructure that was built in previous decades may not meet current requirements. New and rebuilt lines will be upgraded to meet these new code requirements.

Learn what’s next for the Pigs Eye Lake Rebuild Project

Current Status: In December, Xcel Energy began pre-construction activities, including installing matting and access roads, which will be complete by the end of the month. All necessary permits for the project are expected to be received by the end of the year in preparation for construction to begin in January 2026.

What’s Next: Construction is slated to begin in early January 2026. Due to the nature and location of the transmission lines near Pigs Eye Lake, winter construction is ideal because the frozen conditions provide easier access, and construction won’t impact seasonal bird migration. Beginning in January, residents can expect to see construction equipment working in the project area and then in early spring, helicopters will be used to support aspects of the rebuild construction. Target completion for all aspects of the project including habitat restoration is June 2026.

Typical Structures

Steel and Wooden Poles

Timeline

  • Working with local and state agencies to apply for permits to rebuild the project. Agencies involved include Ramsey County, the City of St. Paul, Army Corps of Engineers and others. : Fall/Winter 2024
  • Construction is slated to begin. : August 2025
  • Targeted completion date for construction. : March 2026